edurant.com > MSOE > SEED > Weekly Progress Memos

EE Senior Design: Team ß: Weekly Progress Memos

Quarter Week Subject Date
Spring 10 Display Progress; Loose Ends 13 May 1997
9 Subsystem Integration and Debugging 6
8 Software Progress, Prototype, New Display 29 April
7 Spurious Int. Solved, Fixed Supplies Complete 22
6 Supply Problem Solved, Introl Compiler 15
5 Supply Construction, compiler delays 8
4 Physical Prototyping, more uC work 1
3 Processor and Supply Progress 25 March
2 Processor Change and Supply Progress 18
Winter 10 Not available online 17 February
9 Finalize Specs., Report Preparation 10
8 Subsystem Specifications 3
7 Low V Regulation, Fail-Safing, Error Handling 27 January
6 Digital Control Method 20
5 Processor Selection, Control Prototype 13
4 Control Circuit and I/O Reqs. & Devices 6
3 Revised Supply Block Diagram 16 December 1996
2 Processor Options 9
Fall 9 Further Research & Feasibility Presentation 6 November
8 Feasibility Report Plan and Project Plan 30 October
7 Research (uP, power supplies, interface) 23
6 Features Brainstorming 16
5 Solution Brainstorming 9
4 Final Problem Selection 2

Revised 29 April 1997